Main MenuMain Menu Bookmark PageBookmark Page

Chapter 20

Form 20-5

Additional Clauses for Contractual Mechanic’s Liens

Construction Clause for Mechanic’s Lien Contract

Clause 20-5

1

Project as described in [residential construction contract between/plans and specifications agreed on by] Owner and Contractor.

Force Majeure

Clause 20-5

2

Use this clause under “General Provisions.”

Time is of the essence in the completion and delivery of the Construc­tion. If the Construction is delayed by matters that are beyond the reasonable control of Contractor and that Contractor is unable to prevent or overcome by the exercise of reasonable diligence, the Completion Date will be extended one day for each day the Construction is so delayed, up to a maximum of thirty additional days, provided Contractor notifies Owner of the delay in writing within seven days after its occurrence.

Alternative Payment Terms for Mechanic’s Lien Note

Clause 20-5

3

This note, less the retainage required by statute, is payable on comple­tion of the construction as provided in the mechanic’s lien contract of even date. Completion of construction is determined by [specify]. The retainage, plus interest, is payable as follows: [Contractor must first provide Owner with a written list of all subcontractors and suppliers of any tier who have furnished labor, material, equipment, or other improvements for the Project, including each subcontractor and supplier’s name, address, and telephone number, updated and verified by Contractor as accurate as of the date of final comple­tion of the Project, as a condition precedent to Owner action under this section.  On receipt of the list, Owner will prepare, file, and send an affidavit of comple­tion within ten days of the date of final completion of the Project. Retainage will then be released to Contractor the fiftieth day after the date of final com­pletion as stated in the affidavit, provided no unreleased mechanic’s liens have been filed by that time/On the last business day of the third month after the month of final completion and acceptance of the construction].

Or

Clause 20-5

4

This note is payable in the following installments during progress of the construction as provided in the mechanic’s lien contract [include if applicable: and residential construction contract] of even date:

1.$[amount], less retainage required by statute, on completion of foundation, slab, and preliminary rough plumbing;

2.$[amount], less retainage required by statute, on completion of rough framing;

3.$[amount], less retainage required by statute, on completion of roof and remainder of rough plumbing;

4.$[amount], less retainage required by statute, on completion and acceptance of all construction; and

5.retainage required by statute, which will be paid as follows: [Con­tractor must first provide Owner with a written list of all subcontractors and suppliers of any tier who have furnished labor, material, equipment, or other improvements for the Project, including each subcontractor and supplier’s name, address, and telephone number, updated and verified by Contractor as accurate as of the date of final completion of the Project, as a condition prece­dent to Owner action under this section. On receipt of the list, Owner will pre­pare, file, and send an affidavit of completion within ten days of the date of final completion of the Project. Retainage will then be released to Contractor the fiftieth day after the date of final completion as stated in the affidavit, pro­vided no unreleased mechanic’s liens have been filed by that time/On the last business day of the third month after the month of final completion and accep­tance of the construction].

Or

Clause 20-5

5

This note is payable in the following installments during progress of the construction as provided in the mechanic’s lien contract [include if applicable: and residential construction contract] of even date:

1.$[amount] on [date];

2.$[amount] on [date];

3.at the end of each two-week period after [date], an amount equal to 50 percent of the cost of all labor provided and material in place on the Prop­erty at that time, as estimated by [Contractor/the architect], and not already paid for by Owner, until the total amount paid is $[amount];

4.the balance, plus interest, less retainage required by statute, on or before [date], or on completion of the construction, whichever is later; and

5.retainage required by statute, which will be paid as follows: [Con­tractor must first provide Owner with a written list of all subcontractors and suppliers of any tier who have furnished labor, material, equipment, or other improvements for the Project, including each subcontractor and supplier’s name, address, and telephone number, updated and verified by Contractor as accurate as of the date of final completion of the Project, as a condition prece­dent to Owner action under this section. On receipt of the list, Owner will pre­pare, file, and send an affidavit of completion within ten days of the date of final completion of the Project. Retainage will then be released to Contractor the fiftieth day after the date of final completion as stated in the affidavit, pro­vided no unreleased mechanic’s liens have been filed by that time/On the last business day of the third month after the month of final completion and accep­tance of the construction].

Cost Plus Fixed Fee, Not to Exceed a Certain Amount

Clause 20-5

6

This clause may be placed under “Terms of Payment” or at the end of the mechanic’s lien contract before the notices.

Owner will pay Contractor the actual cost of all labor and materials fur­nished by Contractor and used in the Construction, plus a fixed fee of $[amount]. The total contract price, however, will not exceed $[amount not to exceed that of the mechanic’s lien note]. Contractor will keep an accurate record of the labor and material costs, including all original invoices and receipted bills, and on request will give Owner an accurate, documented accounting of these costs.

Cost Plus Percentage, Not to Exceed a Certain Amount

Clause 20-5

7

This clause may be placed under “Terms of Payment” or at the end of the mechanic’s lien contract before the notices.

Owner will pay Contractor the actual cost of all labor and materials fur­nished by Contractor and used in the Construction, plus [percent] percent of the actual cost of all labor and materials furnished by Contractor and used in the Construction. The total contract price, however, will not exceed $[amount not to exceed that of the mechanic’s lien note]. Contractor will keep an accu­rate record of the labor and material costs, including all original invoices and receipted bills, and on request will give Owner an accurate, documented accounting of these costs.

Liability Disclaimer

Clause 20-5

8

If one spouse will not be liable on the debt, the following clause should be inserted in the mechanic’s lien contract before the signature lines.

[Name of spouse not liable on the debt] is signing this instrument solely to create a lien on the property, and [he/she] is not personally liable on the debt.

Clause for Use with Subordinate/Second Lien Mechanic’s Lien Contract

Insert in mechanic’s lien contract, form 20-1, section A.

Clause 20-5

9

Owner may furnish any insurance required by this mechanic’s lien contract either through existing policies owned or controlled by Owner or through equivalent coverage from any insurance com­pany authorized to transact business in Texas.

Clause 20-5

10

The lien created by this mechanic’s lien contract will be subordinate to the lien securing payment of the note, and any renewals, extensions, and modi­fications thereof, in the original principal amount of [amount] DOLLARS ($[amount]), dated [date], executed by [name], payable to the order of [name], and more fully described in a deed of trust recorded in [recording data] of the real property records of [county] County, Texas. If default occurs in payment of any part of principal or interest of that $[amount] note or in observance of any covenants of the deed of trust securing it, the entire debt secured by this mechanic’s lien contract will immediately become payable at the option of Contractor or its transferees.

Clause 20-5

11

If Owner fails to pay any part of principal or interest secured by a prior lien or liens on the Property when it becomes payable or defaults on any prior lien instrument, the entire debt secured by this mechanic’s lien contract will immediately become payable at the option of Contractor or its transferees.